Skip to main content
23.01.2020

The Janikowo wind project

Eurowind Energy A/S has entered an agreement with Vestas on a 60 MW order for the Janikowo wind project.

The project comprises 29 V100-2.0 MW turbines and one V90-2.0 MW turbine with 120- and 100-meter towers respectively. The project was one of 11 projects that Eurowind Energy A/S won at the Polish wind and solar energy auction in December 2019.

“The Janikowo project marks a Polish market rebound and Eurowind Energy A/S has an increased focus on the Polish market. We are very proud of winning a total of 152 MW in the auction round in Poland with 11 projects”, states Jens Rasmussen, CEO of Eurowind Energy A/S. “We are happy to continue our long-term collaboration with Vestas and look forward to strengthening this cooperation even further”.

Turbine deliveries are expected to begin in the first quarter of 2021, while commissioning is planned for the fourth quarter of 2021. We are looking forward to busy times!

Read the full press release from Vestas below for further comments.

Press Release Janikowo

Back
Be4c5ee9 0D95 4A68 8492 9F92b4af9645